Launching of Badalgama Bridge

The Total Loading , Transporting , Launching , and Aligning were done by WSR Construction. Used 80ton and 50ton crawler cranes for the work along with 25ton rough terrain crane. Same as above we kept the main beams and some of the cross bars, deck plates in the first day. We were able to finish the total job within 4 days as our team worked really hard and worked till midnight. Customer is very happy of this as he could save more additional expenses since we finished it earlier.